Project Management Support for the Three Pharmaceutical Production Units – Saidal Group
Associated Services
Zmirli Production Unit (El Harrach)
Built-up area: 6,000 m²
Dedicated to the production of solid dosage forms (tablets and capsules) with a capacity of 55 million units/year
Contractor: SOFTAL (design and construction)
CNIC’s role: Addressed the contractor’s claims and facilitated the resumption of works that had been halted.
Cherchell Production Unit
Built-up area: 5,000 m²
Dedicated to the production of solid dosage forms (powder sachets and tablets) with a capacity of 25 million units/year
Contractor: BONATTI (design and construction)
CNIC’s role: Demonstrated the unfounded nature of the contractor’s claims (compensation request in a substantial foreign currency amount) and facilitated the resumption of halted construction works.
Constantine Production Unit
Built-up area: 7,200 m²
Dedicated to the production of liquid dosage forms (syrups and sprays) with a capacity of 28 million units/year
Contractor: STE (design and construction)
CNIC’s role: Enabled the resumption of works that had been stopped by providing technical solutions.
| Client | SAIDAL GROUP |
| Location | Algiers, Tipaza, Constantine |
| Period | / |